Winner – Southwest Region
New Lisbon School Parking Lot
Location: New Lisbon
Owner: New Lisbon School District
Concrete Supplier: Croell, Inc.
Contractor/Engineer: Milis Flatwork
General Contractor: Findorff
The New Lisbon School District parking lot was originally designed for asphalt pavement.
After initial discussions with the school district regarding the benefits of concrete pavements, they jumped on board. One year later, construction began on the parking lot.
The parking lot consisted of 95,000 square feet of milling out existing asphalt pavement. It was replaced with 4-inch, 5-inch and 6-inch fiber reinforced concrete pavement.
There was also another 20,000 square feet of concrete overlay of existing asphalt pavement.
The project began on July 5th, 2022 and was completed on July 15th.
In total, 1,600 cubic yards of concrete was poured over 115,000 square feet.